Purchase Requisition

Requisition Type
Requisition No.
Requisition List
REQUISITION_DATENEEDED_BEFOREPRIORITYEMPLOYEE_NAMESEGMENT_CODEREMARK
31/12/202331/12/2023NormalMahmoud Abdelaziz Yousef Sandouqa2023/16252High pressure welder for two days must be Argon Welder certified
Requisition Details List
COST_CNTRITEMITEM_DESCREMARKSREQ_QTYAPRVD_QTYUNITYTD_CONSQTY_ON_HANDREQ_ON_DELIVERYTOTALMIN_QTYMAX_QTYREORDEROPEN_PO
POWER PLANT - MECH MAINT - PP BOILER95110000MAINTENANCE CONTRACT WORKHigh pressure welder for two days must be Argon Welder certified11EA0058353.25800000988410.25
reset
* Note: To reset the PR check the checkbox then reject the task